Project Management
Essay by nehagupta2709 • November 6, 2013 • Coursework • 1,050 Words (5 Pages) • 1,365 Views
1. Project Plan & Project Progress
Activity Activity Earliest Latest
Name Symbol Time Start/Fin Start/Fin Slack
ACT 1 A 4.0000 0.0000 0.0000 0.0000 c
4.0000 4.0000
ACT 2 B 2.0000 4.0000 15.0000 11.0000
6.0000 17.0000
ACT 3 C 6.0000 4.0000 4.0000 0.0000 c
10.0000 10.0000
ACT 4 D 3.0000 6.0000 17.0000 11.0000
9.0000 20.0000
ACT 5 E 10.0000 10.0000 10.0000 0.0000 c
ACT 6 F 2.0000 0.0000 2.0000 2.0000
2.0000 4.0000
ACT 7 G 5.0000 2.0000 15.0000 13.0000
7.0000 20.0000
ACT 8 H 7.0000 2.0000 4.0000 2.0000
9.0000 11.0000
ACT 9 I 1.0000 20.0000 20.0000 0.0000 c
21.0000 21.0000
ACT 10 J 10.0000 9.0000 11.0000 2.0000
19.0000 21.0000
The computations are based on 10 activities
Earliest project completion time = 21.0 weeks
Comments: At the end of week 10, activities A, B, F & H are completed. Activities C, D & G are still in progress while activities E, I & J have not yet started.
Project Plan:
Project Progress:
Jan 9th
2. Schedule Index
Formula used to calculate SI = BCWP/BCWS
Schedule Index Ans Comments
SI for U1 0.77 Behind Schedule
SI
...
...