Project Manager Course Assessment
Completed by: Bhupesh Billimoria
Assessment Activity: 3.2
Develop a Project Scope Statement Definition Document
Activity Instructions: Develop a project scope statement definition for your selected case study using the template heading.
Project Name: Kitchen Renovation
Project Objectives: The project will involve a complete renovation of the existing kitchen based on client specification, which include:
Everything in the kitchen except the crockery, food and cutlery is to go; crockery etc. will need to be stored somewhere - and there is little storage in the house.
Client will need somewhere to make coffee and heat the odd meal - throughout the renovation, and somewhere to keep the milk and other fridge items. Client doesn't want a huge fridge in the lounge room or anywhere else during the renovations.
Paint colour needs to tone with the benches - not sure what finish client wants on the benches - client would like samples and prices for consideration.
Stove, fridge and dishwasher need to be of good quality but not overpriced. Client would like some options. Recommendations will be made based on price and quality.
Client has concerns with her cat being an issue during the renovations as the cat has a habit of running around the house.
Renovations must be completed in five weeks. Client's mother is coming.
Project Scope Description: The project will cover the following parameters:
The team will store owner's identified kitchen equipment
Setup a temporary kitchen
Temporary area to isolate the cat interfering in the project site.
Remove existing kitchen 'junk'
Supply of relevant kitchen equipment
Kitchen equipment appropriate to client specification
Décor requirement based on client specification
Using licenced and qualified trades people for all works.
The total cost of the renovation to cover all cost inclusive of client specification and requirements
Relevant approvals from owner and council
Renovate the existing kitchen to client specification
Project Requirements: A micro look at the scope description:
All works to be carried out to Australian standards and local regulation
All works to be carried out by licenced tradesman
Access required to the building (site) to carry out works
Access required for parking
Payment time line required for works to continue.
Cat to be put in existing room in the house with a gate accessible to the owner so cat remains in the one area.
Project Deliverables: The project aims to deliver the following to the client:
High standard of quality and workmanship
Correct colour coordination - painting
Plan of what the new kitchen will look like
Progress reports of schedules
Temporary kitchen installation plan
Demolition of old kitchen
Renovation works including cabinet works, plumbing electrical and appliances
Isolated area for the cat identified
Final finishing inclusive of completion report of full scope of works
Project Acceptance Criteria: The following criteria will need to be achieved for the project acceptance:
That all works are to Australian standard
All works meet council requirements
All works meets client requirements
The kitchen is fit for purpose
The works are achieved with the timeline period
All works is within budget
There is appropriate waste removal system
The cat is well looked after in its isolated area in the house
The temporary kitchen satisfactory to client during the renovation process.
Project Assumptions and Constraints: the following assumptions have to be made for the project, these include the following:
The building is structurally sound and there will be no impact on the integrity of the building during the renovation process
The working environment is safe for staff, contractors and client
There will be clear and unrestricted access to and from site
Client has legal rights for works
Outlined working hours
Client is in a financial position to pay for works
Builder has access to power water supply for works
All works undertaken have material standard to specification
Timeline
Works must be completed in five weeks from commencement
Budget is fixed
Appliance and equipment availability
Availability of appropriate tradesman
Noise - no works to be carried out before 6am or after 6pm.
Parking on client's property only no parking on neighbour's property
Space and work area is suitable for renovation works
...
...